Our first experience
This was our first project. When we finished and saw
the pictures of the children we knew that we were doing a good thing.
Now that these children have a decent infrastructure to learn we will
be focussing in improving their learning skills. See
our next project.
Altos de la Cruz Remodeling Project
Preparing terrain for Cafeteria |
|
| |
In
early June we sent our first contribution for the remodeling of
the school. We sent $3,000 to Foundation Jera in Cali , Colombia
which is the organization that will be managing the remodeling
of the School. The remodeling started in June 15 and it is expected
to be completed by the end of August 2004.
Status
on July 15, 2004
Water tank: The concrete foundation and the supporting walls for
the tank have been completed.
Toilets: The walls, roof and installation of water pipes are completed.
The facilities will include two regular toilets, 1 urinal and
1 sink. An internal wall was removed to give space to one bathroom
for the teachers.
Status on July 29, 2004
The toilets are almost finished the only thing left is the installation
of the bathrooms' equipment.
The other modifications inside the school are almost completed.
The work to prepare the foundations for the cafeteria started.
We are sending another $2000 to complete the construction.
Status on August 8, 2004
The
ground where the cafeteria was leveled and a retention wall was
built. They are in the process of building a beam to add support
to the retention wall. The exterior of the school is being painted.
Status on August 18, 2004
The beam to support the retention wall was finished. This week
they are letting the ground to settle before starting with the
walls. They painted the interior and exterior and put the doors
for the toilets.
Status on August 23, 2004
They started with cafeteria walls. All of the inside and outside
paint job is completed, They finished closing the wall where the
old main entrance was located.
Status on August 30, 2004
The work is almost finished at the school building. The paint
job is completed. Now they are doing general clean up and electric
installations. The walls for the cafeteria are almost complete.
Status on September 29, 2004
The work is completed! the first day of school after the summer
vacation took place in the middle of September. For most of the
children it was a great surprise to see the school's "new
face" The toilets were the big sensation. For some of the
children it was the first time in their lives they used real toilets.
Some asked "are these toilets for us?" "does it
mean we don't have to go to the out house anymore?" According
to the teachers, the children kept asking every five minutes permission
to go to the toilets.
Detail of expenses until now:
Construction Material: $2650
Labor: $1600
Bathroom equipment $270 |
|
|
| |
Cafeteria Walls |
|
| |
Painting Job indoor
and outdoor |
|
|
|
|
Water tank
|
|
|
|
|
Toilets
|
|
|
|
|
First school day |
|
|
|
|
|
This is your money at
work!